| Drawing of Record Submitted | 6/19/15 |
|---|---|
| Electronic Drawing | 6/19/15 |
| Final Grading Report | 6/19/15 |
| Date Scheduled | 6/23/15 |
| BUILDING PERMIT RELEASE APPROVALS | |
| Power | |
| Water | |
| Wastewater | |
| Engineering | |
| City Development Engineer | |
| Landscaping | |
| FINAL INSPECTION RELEASE APPROVALS | |
| Power | |
| Water | 6/25/2015 Corrections required Per Kevin Condie: 1)Need arrow & line size in collars 2)Break concrete around valve can lids collar 3)Clean & paint hydrant if needed 4)open all valve except stub lines 5)Need to have SO type air gap system on tap at sewer wash -RP 9/17/2015 Approved per Kevin Condie |
| Wastewater | 6/25/2015 Corrections required Per Kevin Condie: 1)Need arrow & line size in collars 2)Break concrete around valve can lids collar 3)Clean & paint hydrant if needed 4)open all valve except stub lines 5)Need to have SO type air gap system on tap at sewer wash -RP 9/17/2015 Approved per Kevin Condie |
| Engineering | 6/24/2015 Corrections required: Sidewalk needs to be finished and handicap stalls not painted. 8/24/2015 Approved per Brandon Wright |
| City Development Engineer | |
| Landscaping | 6/24/2015 Corrections required: Landscaping needs to be complete. 8/24/2015 Approved per Brandon Wright |
| General Comments: | |