Drawing of Record Submitted |
2/13/2015 |
Electronic Drawing |
2/13/2015 |
Final Grading Report |
2/13/2015 |
Date Scheduled |
2/17/2015 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
|
Water |
2/18/2015 Approved per Kevin Condie
03/21/2016 Approved 1 yr warranty per Kevin Condie |
Wastewater |
2/18/2015 Approved per Kevin Condie
03/21/2016 Approved 1 yr warranty per Kevin Condie |
Engineering |
2/18/2015 Approved per Brandon Wright
3/9/2016 Approved 1 year warranty per Brandon Wright
|
City Development Engineer |
|
Landscaping |
4/01/2015 Corrections per Craig Harvey See Attached field inspection report dated 3/30/15.. See Approved Landscape & Irrigation plans dated 2/18/14 attached a copy
4/23/2015 Corrections required Per Craig Harvey.. Need to rake the chat mulch and add additional mulch in some areas where it appears thin still short 5 live oaks as shown on plan, Fence installer needs to clean up concrete debris & construction waste off the landscape strip along the blockwall
5/19/15 - approved per Craig Harvey |
| |
General Comments: |
2/19/15 received completion and warranty bond (GS) |