| Drawing of Record Submitted | 3/23/2015 |
|---|---|
| Electronic Drawing | 3/23/2015 |
| Final Grading Report | 3/23/2015 |
| Date Scheduled | 3/26/2015 |
| BUILDING PERMIT RELEASE APPROVALS | |
| Power | |
| Water | |
| Wastewater | |
| Engineering | |
| City Development Engineer | |
| Landscaping | |
| FINAL INSPECTION RELEASE APPROVALS | |
| Power | |
| Water | 3/27/2015 Approved per Kevin Condie 3/2/2016 Approved 1 year warranty per Kevin Condie |
| Wastewater | 3/27/2015 Approved per Kevin Condie 3/2/2016 Approved 1 year warranty per Kevin Condie |
| Engineering | 3/27/2015 Approved per Brandon Wright 3/11/2016 Approved 1 year warranty per Brandon |
| City Development Engineer | |
| Landscaping | 3/27/2015 Approved per Craig Harvey |
| General Comments: | |
| received warranty bond 3/31 (gs) | |