St George Holiday Inn
Number: Grading-47891

Drawing of Record Submitted 01/06/2016
Electronic Drawing 01/06/2016
Final Grading Report 01/06/2016
Date Scheduled 01/07/2016
BUILDING PERMIT RELEASE APPROVALS
Power
Water
Wastewater
Engineering
City Development Engineer
Landscaping
FINAL INSPECTION RELEASE APPROVALS
Power
Water 01/11/2016 Corrections required: 1) Waiting for (2) Backflow tests 01/13/2016 Corrections required: 1) Need to have the backflow assembly on the fire riser tested and tagged. 2) Need the backflow assembly in the meter pit tested and tagged. 3) Need the curb painted red and the fire hydrant at the northwest corner of the parking lot. 01/19/2016 Approved per Carson Tait
Wastewater 01/11/2016 Corrections required: 1) Waiting for (2) Backflow tests 01/13/2016 Corrections required: 1) Need to have the backflow assembly on the fire riser tested and tagged. 2) Need the backflow assembly in the meter pit tested and tagged. 3) Need the curb painted red and the fire hydrant at the northwest corner of the parking lot. 01/19/2016 Approved per Carson Tait
Engineering 01/11/2016 Corrections required 1) Site is not cleaned up for final 2) Adjacent property needs to be cleaned up 3) Trash enclosure gates not hung. per Brandon Wright 01/13/2016 Approved per Brandon Wright
City Development Engineer
Landscaping 01/07/2016 Corrections required 1) Landscape at rear of building not complete 2) Streetscape is finished 3)Construction trash Debris needs to be removed and cleaned off of all landscaped areas - including streetscape per Craig Harvey 1/19/2016 Approved per Craig Harvey
    
General Comments: