Drawing of Record Submitted |
08/27/2004 |
Electronic Drawing |
|
Final Grading Report |
08/27/2004 |
Date Scheduled |
|
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
|
Water |
08/31/2004 Approved Per Carson Tait. Thank you, Nice Job |
Wastewater |
08/31/2004 Approved Per Carson Tait. Thank you, Nice Job |
Engineering |
09/02/2004 Corrections required. Per Mike Hester. Install sidewalk and ADA ramps on commerce Dr. as per the approved plans.
09/09/2004 Corrections required per Mike Hester. . Install sidewalk on commerece Drive as per the approved plans.
09/20/2004 Approved Per Mike Hester |
City Development Engineer |
09/20/2004 Approved per Jay Sandberg |
Landscaping |
09/29/2004 Approved Per Doug W. |
| |
General Comments: |
11/24/03 Response to Clay Tolbert of McNeil Eng. was informed by Mark Bradley in July of 2003 of required plan adjustments. To date adjustments have not been made. Inquiries by Clay have been made recently wherein he was informed that a grading permit could not be issued until construction/site drawings were approved through Engineering. Issuance of a grading permit is awaiting approvals. |