Springs Phase VII & VIII, The
Number: Grading 30281

Drawing of Record Submitted
Electronic Drawing
Final Grading Report
Date Scheduled
BUILDING PERMIT RELEASE APPROVALS
Power
Water
Wastewater
Engineering
City Development Engineer
Landscaping
FINAL INSPECTION RELEASE APPROVALS
Power
Water 3/31/04 - Corrections required per Jeff Lance. Need to clean valve can lids. Need to replace two meter pads. Corp stop too close to box, move setter or box. Still need to check wire. Need to straighten fire hydrants with street. 05/11/2004. Approved per Kevin Condie(setter on lot 69). 5/07/2004. Final Approved per Kevin C.
Wastewater 3/31/04 - Corrections required per Jeff Lance. Need to clean valve can lids. Need to replace two meter pads. Corp stop too close to box, move setter or box. Still need to check wire. Need to straighten fire hydrants with street. 05/11/2004. Approved per Kevin Condie(setter on lot 69). 5/07/2004. Final Approved per Kevin C.
Engineering 3/30/04. Corrections required per Mike Hester. Complete the drawing of records. Grout the street light bases. Replace all damaged sidewalks. Install stop sign at 2580 E and Springs Dr/Lake Dr. 4/21/04 approved per Mike Hester.
City Development Engineer 3/30/04. Corrections required per Judd Burgess. Final plat needs to be recorded. 4/21/04. Corrections required per Judd Burgess. Final plats need to be recorded. 02/08/2005 Approved or Phase 7 & 8 per Cathy Hasfurther
Landscaping 3/30/04. Approved per Mark Bradley. Check/bond received.
    
General Comments: