| Drawing of Record Submitted | 02/15/2005 (only 2 copys) 03/07/05 new copies |
|---|---|
| Electronic Drawing | |
| Final Grading Report | 02/28/2005 |
| Date Scheduled | |
| BUILDING PERMIT RELEASE APPROVALS | |
| Power | |
| Water | |
| Wastewater | |
| Engineering | 02/16/2005 Approved per Mike Hester.. Permits Only |
| City Development Engineer | 02/18/2005 Corrections required per Cathy.. Final plat needs to be recorded, file bond for public improvements, final assessment for SID to be paid. |
| Landscaping | |
| FINAL INSPECTION RELEASE APPROVALS | |
| Power | |
| Water | 02/16/2005 Corrections required per Allen Briggs.. W in curb and new lid on lot #6, #1 remove concrete from bolt on lot #5 hydrant remove concrete from meter setter lot #9,#3. 02/22/2005 Corrections required per Allen: Punch list items completed will final when drawing of recorded is re-summitted. 03/01/2005 Approved per Allen Briggs |
| Wastewater | 02/16/2005 Corrections required per Allen Briggs.. W in curb and new lid on lot #6, #1 remove concrete from bolt on lot #5 hydrant remove concrete from meter setter lot #9,#3. 02/22/2005 Corrections required per Allen: Punch list items completed will final when drawing of recorded is re-summitted. 03/01/2005 Approved per Allen Briggs |
| Engineering | 03/01/2005 Corrections required per Mike Hester.. NOT READY.. 03/02/2005 Corrections required per Cathy.. Electronic DWG of records, rip rap on the upstream and downstream .Curb an gutter per plan along 2350 East 03/04/2005 Complete all monumentation.. Clean the public improvements. correct the Drawing of Records. 03/09/2005 Approved per Mike Hester |
| City Development Engineer | 03/09/2005 Approved per Cathy H |
| Landscaping | 02/28/2005 Approved per Mark Bradley N/A |
| General Comments: | |
| Grading permit issued on 9/9/04. 7500 cubic yards of excavation. Construction drawing circulating for signature. | |