Drawing of Record Submitted |
|
Electronic Drawing |
|
Final Grading Report |
|
Date Scheduled |
|
BUILDING PERMIT RELEASE APPROVALS |
Power |
4-11-01 Corrections Required per Don Higgins - Consultation meeting to determine what needs to be done - no power available |
Water |
4-13-01 Corrections Required per Kevin -Consultation meeting to determine what needs to be done - change setter, rechloridate & pressure test |
Wastewater |
4-13-01 Corrections Required per Kevin -Consultation meeting to determine what needs to be done - change setter, rechloridate & pressure test |
Engineering |
4-11-01 Corrections Required per Mike Heston - 1)Provide an interum grading report for all underground installations, curb & gutter and cross gutters, conrete testing - 2)Remove all debris and reprocess the roadway sub-grade then base and compact - 3)Address the lot drawings problems, most are too low - 4)Install the gas crossing sleeves - 5)Engineering need to approve revised civil plans |
City Development Engineer |
4-05-01 Corrections Required per Jack Voris - 1)Provide revised civil drawings - 2)grade lots to drain (fill) - 3)test water, sewer, power - 4)Provide compaction tests for sewer water power trenching |
Landscaping |
5-01-01 Approved per Doug Wulfenstein |
FINAL INSPECTION RELEASE APPROVALS |
Power |
9-06-00 Corrections Required per Don Higgins - We do not even have an approved plan. Power system will need to be completely installed and energized. |
Water |
9-07-00 Corrections Required per Kevin - Need to have week removed so we can see what is there - Need to re-chlorinate, flush, pressure test, setters, boxes, concrete collars on boxes and valve and hydrants - there may be more than this? |
Wastewater |
9-07-00 Corrections Required per Kevin - Need to have week removed so we can see what is there - Need to re-chlorinate, flush, pressure test, setters, boxes, concrete collars on boxes and valve and hydrants - there may be more than this? |
Engineering |
9-06-00 Corrections Required per Mike Hester - Clear the weeds & brush in the road & r/w so an inspection can be made. |
City Development Engineer |
Approved per Jack Voris |
Landscaping |
9-06-00 Approved per Doug Wulfenstein |
| |
General Comments: |
|