Drawing of Record Submitted |
02/02/2005 phase 1..Phase II 04/26/2005-Phase III 5-25-05 |
Electronic Drawing |
02/02/2005 phase 1.. Phase II 04/26/2005--Phase III-05-25-05 |
Final Grading Report |
02/02/2005 phase1..Phase II 04/26/2005 ..Phase III 05/20/2005 |
Date Scheduled |
02/03/2005..04/28/2005--05-31-05 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
10/15/2004 Approved per Dennis Wright Permits only Phase 1 ONLY
Approved per Dennis Wright Permits only for phase 3. |
Water |
10/22/2004 Approved per Kevin Condie for Permits only... no permits on 1800 North there are no setters.
Phase 1 ONLY |
Wastewater |
10/22/2004 Approved per Kevin Condie for Permits only... no permits on 1800 North there are no setters.
Phase 1 ONLY |
Engineering |
10/15/2004 Approved and corrections required per Larry Henderson.. Drawing of record and final grading report.
PHASE 1 ONLY
07/14/2005 Approved per Larry Henderson PHASE 2 ONLY. |
City Development Engineer |
10/21/2004 Approved per Jay Sandberg.. For Permits Only PHASE 1 ONLY
05/03/2005..Approved Phase 2 .. per Jay Sandberg..Permits Only Final plat not recorded.
07/15/2005 Approved per Jay Sandberg For Phase 3 only |
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
02/03/2005 Approved per Dennis Wright Phase 1
04/28/2005 Approved Dennis Wright Phase 2
06/02/2005 Corrections required per Dennis Wright, Phase 3 will give for Permits only..
07/18/2005 Approved per Dennis Wright Phase 3 Only.
06/09/2006 Approved pre Dennis Wright.. 1 year warranty |
Water |
02/04/2005 Approved per Kevin Phase 1
04/29/205 Corrections required per Kevin oOndie For Phase 2..1. Replace Hyd on lot #34 broken. 2. Clean hydrants and paint. 3. Need to check wire. Look Good. 4. If hydrants or meter fall into sidewalk they will have to be move by Owen.
05/05/2005 Approved per Kevin Condie.Phase 2 only
06/01/2005 Corrections required per Travis Shelly Phase 3.. Flush all lines, clean out concrete in m/h infront of lot #48. Need step in m/h infront of lot #80. Clean m/h in lot #87. Need c/o cap on lot #65,#69. Can't final until Tuweep Drive is paved to 1575 West.
06/02/2005 Approved per Kevin Condie.. Need Final on Tuweep Drive 6/12/06-1 year warranty - Corrections Required per Kevin Condie - Water line trench by fire hydrant line has dropped and broken up at 2180 W & 1740 N and in the intersection of 2130 W & 1740 N; 2190 W & 1740 N. |
Wastewater |
02/04/2005 Approved per Kevin Phase 1
04/29/205 Corrections required per Kevin oOndie For Phase 2..1. Replace Hyd on lot #34 broken. 2. Clean hydrants and paint. 3. Need to check wire. Look Good. 4. If hydrants or meter fall into sidewalk they will have to be move by Owen.
05/05/2005 Approved per Kevin Condie.Phase 2 only
06/01/2005 Corrections required per Travis Shelly Phase 3.. Flush all lines, clean out concrete in m/h infront of lot #48. Need step in m/h infront of lot #80. Clean m/h in lot #87. Need c/o cap on lot #65,#69. Can't final until Tuweep Drive is paved to 1575 West.
06/02/2005 Approved per Kevin Condie.. Need Final on Tuweep Drive 6/12/06-1 year warranty - Corrections Required per Kevin Condie - Water line trench by fire hydrant line has dropped and broken up at 2180 W & 1740 N and in the intersection of 2130 W & 1740 N; 2190 W & 1740 N. |
Engineering |
02/04/2005 Corrections required per Larry Henderson Sagewood Phase 1 only.. backfill behind curbs, complete sidewalk, backfill block wall along East property line, Shoulder asphalt in 1800 North with rad base. Remove forms from water meter pads, Geotech certification for rock walls. ramp ends of sidewalk, replace water meter pad lot ( 9 & 10, North 2130 change manhole lid for storm drain lid install monuments.
02/08/2005 Approved per Larry Henderson Phase 1
04/29/2005 Corrections required per Larry Henderson. Phase 2 only. Backfill behind curbs, replace broken curb @ inlet box 1740 North 2190 West, seal curb crack,clean off spilled concrete, get palletts off of curb. Approved for permits only - Jay Sandberg
05/19/2005 Approved per Larry Henderson Phase 2.
06/01/2005 Corrections required per Larry Henderson ..Phase 3. Street lights, sidewalks, clean out inlet boxes, complete monuments, Tuweep Dr? walls?
07/14/2005 Corrections required per Larry Henderson..Sign @ Tuweep and 1575 North too low.. Check all signs clean stret.. Finish curb backfill, Check mediam curb height Tuweep.
07/15/2005 Approved per Larry Henderson Phase 3 only |
City Development Engineer |
02/03/2005 Approved per Jay Sandberg phase 1
05/03/2005 PERMITS ONLY!! Phase 2 only Approved per Jay Sandberg. Final plat not recorded.
06/03/2005 Corrections required per Jay Sandberg Out of spec asphalt to be replaced.
07/20/2005 Approved per Jay Sandberg..Phase 2 only.. Asphlat problem resolved.. report updated.
08/22/2005 Ok For Permits Per Jay until 9-2-05.. Signing not complete
09/08/2005 Approved per Jay Sandberg
8/3/06 1 year warranty (City Project Engineer) Corrections Required PHASE II per Ken B - Large aggregate on pavement at 1800 N Tueweap Dr. Chips missing in curb, trash in storm drain, chunks in pavement at street.
8/4/06 - 1 year warranty inspection Phase III Approved per Ken B |
Landscaping |
02/04/2005 Corrections required per Matt C. No Trees to inspect.
02/08/2005 Approved per Matt Callister.. As per conditions for meeting requirements with City Bond.
Temporary approval- Bond place W/Jay Sandberg Due to weather conditions- Trees must be installed prior to release of bond.
05/05/2005 Approved Per Matt C.. For Phase 2 only
06/06/2005 Approved per Doug W.
07/15/2005 Corrections required per Mark Bradley. Phase 3 only. Replace median curb,remove rock as discussed with Colleen.
8/3/06 1 year warranty (PARKS) Approved per Ken B.
8/4/06 - 1 year warranty inspection Phase III Approved per Ken B |
| |
General Comments: |
SAGEWOOD (phase 1) only HAS BEEN RELEASED FOR PERMITS. |