| Complete Plans Submitted | 3/17/2016 |
|---|---|
| Sent For Structural Review | |
| 1st Plan Review Completed | 4/6/2016 |
| Returned From Arch / Engineer For Re-review | |
| Returned To Arch / Engineer For Futher Corrections | |
| Plan Review Approved | 4/18/16 |
| Permit Issued | |
| General Comments: | |
| 3/17/2016 received plans 3/17/2016 distributed to Dave for review 4/6/2016 out for corrections 4/21/2016 Ready to permit | |