Pinebrook North Phase II
Number: Grading 34052

Drawing of Record Submitted 09/12/2005
Electronic Drawing 09/12/2005
Final Grading Report
Date Scheduled
BUILDING PERMIT RELEASE APPROVALS
Power 08/04/2005 Approved per Dennis Wright
Water 08/04/2005 Corrections Required per Kevin Condie..Valve need to be up to grade and concrete collar around meter setters. Need water to hydrants. 08/10/2005 Corrections required per Kevin Condie. Valve on Indian Hills Dr need to be at subgrade 09/07/2005 Corrections required per Kevin Conide.. NOT READY.. Valve need to be raised in project and on Indian Hills, check wire, fire hydrant collar need to run into curb, clean hydrants and paint,meter for church need collar and w/rebar need to check meter setters.. Not ready 09/08/2005 Approved per Kevin Condie.. Permits Only.. Not a Final
Wastewater 08/04/2005 Corrections Required per Kevin Condie..Valve need to be up to grade and concrete collar around meter setters. Need water to hydrants. 08/10/2005 Corrections required per Kevin Condie. Valve on Indian Hills Dr need to be at subgrade 09/07/2005 Corrections required per Kevin Conide.. NOT READY.. Valve need to be raised in project and on Indian Hills, check wire, fire hydrant collar need to run into curb, clean hydrants and paint,meter for church need collar and w/rebar need to check meter setters.. Not ready 09/08/2005 Approved per Kevin Condie.. Permits Only.. Not a Final
Engineering 08/04/2005 Correctiosn Required per Larry Henderson.. Complete base, ashphalt and SW 08/10/2005 Corrections required per Larry Henderson.. Project not complete 09/08/2005 Approved per Larry Henderson
City Development Engineer 09/08/2005 Approved per Jay Sandberg..Permits Only
Landscaping
FINAL INSPECTION RELEASE APPROVALS
Power 09/21/2005 Approved per Dennis W. 11/2/06 1 year warranty Approved per Dennis Wright.
Water 09/16/2005 Corrections required per Kevin Condie 1. No arrow in concrete collars, 2. No Number in concrete collars (pipe Size..)3. Meter for church hs no collar around it 4. Clean and paint hydrants.5. Need to check hydrant valve and wire. 6. Meter pad on lot 3 is broken. 10/21/2005 Approved per Kevin Condie 11/7/06 1 year warranty Approved per Kevin Condie.
Wastewater 09/16/2005 Corrections required per Kevin Condie 1. No arrow in concrete collars, 2. No Number in concrete collars (pipe Size..)3. Meter for church hs no collar around it 4. Clean and paint hydrants.5. Need to check hydrant valve and wire. 6. Meter pad on lot 3 is broken. 10/21/2005 Approved per Kevin Condie 11/7/06 1 year warranty Approved per Kevin Condie.
Engineering 09/15/2005 Corrections required per Larry H.. Backfill behind curb and sidwalk,complete sidewalk on Indian Hills, install street lights,seal cracks in curb, trim expansion joints,remove block and material from street, complete entry. install monuments, remove construction debris, cover inlet lot 8 to prevent trash in line 12/12/2005 Approved per Larry Henderson 1/2/07 1 year warranty - Corrections required per Brandon Wright. Sunken and cracked concrete around meter boxes. Cracked curbs.
City Development Engineer 09/26/2005 Corrections required per Jay Sandberg.. Final plat not signed by City Attty. or City Engineer 12/23/2005 Approved per Jay Sandberg 11/14/06 - 1 year warranty - Approved per Ken B.
Landscaping 10/18/2005 Approved per Mark Bradley.. N/A ..City Maintained Site along Indian Hills Drive 11/08/2005 Approved per Doug W. N/A 11/14/06 - 1 year warranty - Approved per Ken B.
    
General Comments: