Drawing of Record Submitted |
|
Electronic Drawing |
|
Final Grading Report |
|
Date Scheduled |
|
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
8/20/2008 N/A This does not apply to St George Power Per Dennis Wright |
Water |
8/25/2008 Corrections required per Carson Tait.. Need to replace the broken meter box. Pour concrete pads around the Fire hydrant,valve box,and meter box. Mark direction of flow arrow and line size into the valve box concrete. |
Wastewater |
8/25/2008 Corrections required per Carson Tait.. Need to replace the broken meter box. Pour concrete pads around the Fire hydrant,valve box,and meter box. Mark direction of flow arrow and line size into the valve box concrete. |
Engineering |
|
City Development Engineer |
8/20/2008 Approved per Ken Bricker |
Landscaping |
8/20/2008 Approved Per Ken Bricker |
| |