Drawing of Record Submitted |
06/10/2005 |
Electronic Drawing |
06/10/2005 |
Final Grading Report |
01/27/2005 |
Date Scheduled |
06/14/2005 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
06/16/2005 Approved per Dennis Wright.. The Only parts of the Plaza Finaled are Ashley Furniture and The Threaters. |
Water |
06/14/2005 Corrections required per Tim Jones.. Nothing corrected from last Final Punch List..
08/01/2005 Corrections required per Boyd.. Concrete all valves. Fire Hydrant and meter boxes.
09/16/2005 Corrections required per Tim.. No drawing of records. Valve collars in 2450 E have no pipe sizes cut into collar. Meter box on corner of Red Cliffs Dr and 2450 E needs pad poured around. Meter boxes in front of Ashley Furn. need pads poured. Valve collar in middle entry needs arrows and pipe sizes, meter boxes and hydrant on Red Cliffs Dr by middle entry need pads poured. Hydrant on Western Entrance needs pad poured. Meter box for Ashley Furn needs pad poured. Valve collar on 2450 E south end Ashley Furn needs pipe size cut in. Hydrant in front of Stadium 10 has no locate wire. All hydrants need to be cleaned and painted on extensions.
09/28/2006 Corrections required per Tim Dotson.. See Punch list |
Wastewater |
06/14/2005 Corrections required per Tim Jones.. Nothing corrected from last Final Punch List..
08/01/2005 Corrections required per Boyd.. Concrete all valves. Fire Hydrant and meter boxes.
09/16/2005 Corrections required per Tim.. No drawing of records. Valve collars in 2450 E have no pipe sizes cut into collar. Meter box on corner of Red Cliffs Dr and 2450 E needs pad poured around. Meter boxes in front of Ashley Furn. need pads poured. Valve collar in middle entry needs arrows and pipe sizes, meter boxes and hydrant on Red Cliffs Dr by middle entry need pads poured. Hydrant on Western Entrance needs pad poured. Meter box for Ashley Furn needs pad poured. Valve collar on 2450 E south end Ashley Furn needs pipe size cut in. Hydrant in front of Stadium 10 has no locate wire. All hydrants need to be cleaned and painted on extensions.
09/28/2006 Corrections required per Tim Dotson.. See Punch list |
Engineering |
08/02/2005 Corections required per Larry Henderson. Nothing on previous punch list done(6-14-05)
09/19/2005 Corrections required per Larry H.. Met with Bill and discussed s/w backfill as prioity for public safety |
City Development Engineer |
08/02/2005 Approved per Jay Sandberg For Phase 1 Only (Furniture Store and Theatres.Bldg #400.) |
Landscaping |
08/02/2005 Corections required per Ray Synder..City Forester to review street tree requirements.
08/02/2005 Corrections required per Matt C. 1. Plant trees on South Side of Red Cliffs Dr according to comm.
Forestry plan. Trees on Northside do no meet agreement between developer and City.to replace existing trees. Problems should be addressed through Kent Perkins.
09/16/2005 Corrections required per Doug W... No Trees
09/21/2005 Corrections required per Ray S. Satisfy City Forester that street ordinance has been complete with
10/02/2006 Approved Per Jay Sandberg |
| |
General Comments: |
|