St. George Food Bank Expansion

JUC STATUS
Current Status Review Required
JUC 1st Review 08/03/2021
JUC 2nd Review
JUC 3rd Review
JUC 4th Review
JUC Approved
JUC Comments:
7/26/2021- Rcvd JUC checklist and plans for 1st Review 8/3/2021 - JUC comments returned to engineer. 12/10/2021- Rcvd JUC checklist and plans for 2nd review 1/20/2022- Rcvd revised JUC plans for approval
CONSTRUCTION DRAWING STATUS
Current Status Returned to Engineer
1st Review 11/08/2021
2nd Review 01/11/2022
3rd Review
Final Approval
4th Review
Construction Review Comments:
9/16/2021- Rcvd SPR app, fees, plans, Drainage rpt, CAD, Soils rpt and grading permit app. 12/10/2021 - Rcvd SPR revised plans, grading app and drainage rpt for 2nd review Submission Documents SPR Application- 9/16/2021 SPR Fee- 9/17/2021 LID Grading Permit Application- 9/16/2021 Drainage Study Digital- 9/16/2021 Geotechnical Report Digital - 9/16/2021 CAD Site Plan (dwg format)-9/16/2021