| JUC STATUS | |
|---|---|
| Current Status | Review Required |
| JUC 1st Review | 08/03/2021 |
| JUC 2nd Review | |
| JUC 3rd Review | |
| JUC 4th Review | |
| JUC Approved | |
| JUC Comments: | |
| 7/26/2021- Rcvd JUC checklist and plans for 1st Review 8/3/2021 - JUC comments returned to engineer. 12/10/2021- Rcvd JUC checklist and plans for 2nd review 1/20/2022- Rcvd revised JUC plans for approval | |
| CONSTRUCTION DRAWING STATUS | |
| Current Status | Returned to Engineer |
| 1st Review | 11/08/2021 |
| 2nd Review | 01/11/2022 |
| 3rd Review | |
| Final Approval | |
| 4th Review | |
| Construction Review Comments: | |
| 9/16/2021- Rcvd SPR app, fees, plans, Drainage rpt, CAD, Soils rpt and grading permit app. 12/10/2021 - Rcvd SPR revised plans, grading app and drainage rpt for 2nd review Submission Documents SPR Application- 9/16/2021 SPR Fee- 9/17/2021 LID Grading Permit Application- 9/16/2021 Drainage Study Digital- 9/16/2021 Geotechnical Report Digital - 9/16/2021 CAD Site Plan (dwg format)-9/16/2021 | |