Drawing of Record Submitted |
08/02/2005 4 copies |
Electronic Drawing |
08/02/2005 |
Final Grading Report |
09/13/2005 |
Date Scheduled |
|
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
08/02/2005 Approved per Dennis Wright.. Clearances from switches landscape rocks.
11/2/06 1 year warranty Approved per Dennis Wright. |
Water |
08/03/2005 Corrections required per Kevin Condie..Concrete valves,concrete meter boxes,concrete hydrants, raise air vac 1250 North and valve, check wire,Raise valve by PRV,Not Ready,Need to check valve and meters
10/14/2005 Approved per Kevin Condie.. Hydrant South of Round about need to be moved back in next phase.. Paint Hydrants
10/10/06 Approved per Tim Dotson
11/13/06 1 year warranty - Corrections Required per Kevin Condie. See first punch list. Finish it then call for warranty. |
Wastewater |
08/03/2005 Corrections required per Kevin Condie..Concrete valves,concrete meter boxes,concrete hydrants, raise air vac 1250 North and valve, check wire,Raise valve by PRV,Not Ready,Need to check valve and meters
10/14/2005 Approved per Kevin Condie.. Hydrant South of Round about need to be moved back in next phase.. Paint Hydrants
10/10/06 Approved per Tim Dotson
11/13/06 1 year warranty - Corrections Required per Kevin Condie. See first punch list. Finish it then call for warranty. |
Engineering |
08/02/2005 Corrections required per Larry Henderson.. Complete project --then call
10/11/2005 Corrections required per Larry Henderson.. Still have sidewalk and curb missing
01/05/2006 Approved per Larry Henderson
1/22/07 - 1 year warranty - Approved per Brandon Wright. |
City Development Engineer |
12/22/2005 Approved per Jay Sandberg |
Landscaping |
08/02/2005 Corections required per Ray Synder..Landscape not in..trash enclosure not in
11/29/2005 Corrections required per Doug W.. NO TREE'S
12/15/2005 Approved per Ray Synder.. N/A.. Doug W. (Parks) to Final still.
12/16/2005 Approved per Lynn Scott.. N/A grading for plan 2. Park Dept to final LS |
| |
General Comments: |
|