Southgate Hills Phase IV
Number: Grading 28250

Drawing of Record Submitted 03/19/2003
Electronic Drawing
Final Grading Report 03/19/2003
Date Scheduled 03/20/2003
BUILDING PERMIT RELEASE APPROVALS
Power
Water
Wastewater
Engineering
City Development Engineer
Landscaping
FINAL INSPECTION RELEASE APPROVALS
Power 04/14/2003 Approved per Don Higgins.
Water 03/20/2003 Approved per Carson Tait. Need rebar in one box.Make shut off valve accessible in one box. Setter is tight against the backside of one box.Need at least one inch clearance. 03/28/2003 Approved per Carson Tait
Wastewater 03/20/2003 Approved per Carson Tait. Need rebar in one box.Make shut off valve accessible in one box. Setter is tight against the backside of one box.Need at least one inch clearance. 03/28/2003 Approved per Carson Tait
Engineering 03/20/2003 Corrections Required per Larry Henderson Trim expansion joints Ramp end of sidewalks Remove debris from south side of Rolling Hills Dr. Backfill behind sidewalk on Rolling Hills Dr Remove form from meter pads Install street lights Remove incorrect street signs from SE corner 03/27/2003 Corrections required per Larry Henderson - no punchlist items have been done. 04/01/2003 Approved per Larry Henderson.
City Development Engineer 03/21/2003 Corrections Required per Judd Burgess. Verification of compliance for hillside permit. Final plat recorded. 04/09/2003 Approved per Judd Burgess
Landscaping 03/20/2003 Approved per Mark Bradley
    
General Comments: