| Drawing of Record Submitted | 09/19/2005 |
|---|---|
| Electronic Drawing | 09/19/2005 |
| Final Grading Report | 09/19/2005 |
| Date Scheduled | 09/20/2005 |
| BUILDING PERMIT RELEASE APPROVALS | |
| Power | |
| Water | |
| Wastewater | |
| Engineering | |
| City Development Engineer | |
| Landscaping | |
| FINAL INSPECTION RELEASE APPROVALS | |
| Power | 09/21/2005 Approved per Dennis Wright |
| Water | 09/20/2005 Corrections required per Kevin Condie. Redo collar in street-concrete is broken. 2. test backflow, 3. Lower meter setter and box to grade of landscaping.4. After meter box is lowered put concrete around it w/rebar through box. 5. Fire sprinkler valve is off, 6. Arrow and line size on fire sprinkler valve 09/30/2005 Approved per Boyd Rowndy |
| Wastewater | 09/20/2005 Corrections required per Kevin Condie. Redo collar in street-concrete is broken. 2. test backflow, 3. Lower meter setter and box to grade of landscaping.4. After meter box is lowered put concrete around it w/rebar through box. 5. Fire sprinkler valve is off, 6. Arrow and line size on fire sprinkler valve 09/30/2005 Approved per Boyd Rowndy |
| Engineering | 09/20/2005 Corrections required per Larry H. Clean gutters, seal cracks in curb, scraps off spilled concrete 09/24/2005 Approved per Larry Henderson 09/27/2005 Approved per Larry Henderson |
| City Development Engineer | 09/21/2005 Approved per Jay Sandberg |
| Landscaping | 09/21/2005 Approved per Ray Synder |