| Drawing of Record Submitted | 10/05/2005 |
|---|---|
| Electronic Drawing | 10/05/2005 |
| Final Grading Report | 10/05/2005 |
| Date Scheduled | 10/11/2005 |
| BUILDING PERMIT RELEASE APPROVALS | |
| Power | |
| Water | |
| Wastewater | |
| Engineering | |
| City Development Engineer | |
| Landscaping | |
| FINAL INSPECTION RELEASE APPROVALS | |
| Power | |
| Water | 10/11/2005 Approved per Carson Tait.. Need to move re-bar to the side in the meter box. |
| Wastewater | 10/11/2005 Approved per Carson Tait.. Need to move re-bar to the side in the meter box. |
| Engineering | 10/11/2005 Approved per Larry Henderson |
| City Development Engineer | |
| Landscaping | |
| General Comments: | |