Drawing of Record Submitted |
4 copies 11/21/2005 |
Electronic Drawing |
11/21/2005 |
Final Grading Report |
11/23/2005 |
Date Scheduled |
11/29/2005 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
11/29/2005 Approved per Dennis Wright |
Water |
11/30/2005 Corrections required per Kevin Condie..1. RD(backflow) is before fresh water side need to move fresh water to supply side of backflow.2. Test backflow. 3. May need to put backflow on window washer make-up water-- need to see msds paper.
9/19/2007 Approved per Kevin Condie |
Wastewater |
11/30/2005 Corrections required per Kevin Condie..1. RD(backflow) is before fresh water side need to move fresh water to supply side of backflow.2. Test backflow. 3. May need to put backflow on window washer make-up water-- need to see msds paper.
9/19/2007 Approved per Kevin Condie |
Engineering |
11/29/2005 Corrections required per Larry.. Clean out drop inlet boxes clean up const. debris, submit rock wall certifications, uncover inlet in front of car wash, grout around pipes in inlet boxes
12/01/2005 Approved per Larry Henderson |
City Development Engineer |
12/22/2005 Approved per Jay Sandberg |
Landscaping |
11/30/2005 Corrections required per Ray Synder.. Install solid metal gates on trash enclosue per approved plan
1/03/2008 Approved per Ken Bricker.. Already in Busines |
| |
General Comments: |
|