Drawing of Record Submitted |
10/17/2006 |
Electronic Drawing |
10/17/2006 |
Final Grading Report |
12/07/2006 |
Date Scheduled |
12/11/2006 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
07/05/2006 Corrections required per Dennis Wright NOT READY
07/14/2006 Corrections required per Dennis Wright.. NOT READY
10/12/06 Approved for Permits ONLY per Dennis Wright. |
Water |
10/2/06 Corrections required per Tim Dotson. Collars need to be replaced.
10/12/06 Approved per Tim Dotson. Per Spec. Check all meter boxes and setters valve can collars and arrows in collars hydrants need to be raised up on some of them. |
Wastewater |
10/2/06 Corrections required per Tim Dotson. Collars need to be replaced.
10/12/06 Approved per Tim Dotson. Per Spec. Check all meter boxes and setters valve can collars and arrows in collars hydrants need to be raised up on some of them. |
Engineering |
07/05/2006 Corrections required per Carlos Robles.. Finish Project
9/28/06 Corrections required per Carlos Robles. Cut pipe inside inlet boxes - all boxes need to be cleaned. Seal cracked sidewalks and curbs, patch and fix sidewalk and curb. Backfill behind sidewalks, ramp off sidewalks. Street lights, street sings. Install end of road signs. Finish sidewalk, remove dirt, rocks, concrete, from curbs. Sewer, water and power must be approved.
09/28/2006 Corrections required per Carlos Robles..Cut pipe inside inlet boxes-all boxes need to be cleaned, seal cracked sidewalks and curbs,patch and fix sidewalk and curb, backfill behind sidewalks, ramp off sidewalks.street lights, street signs. Install end of end of road signs. Finish sidewalk,remove dirt, rocks, concrete from curbs sewer,water and power must be approved.
10/12/2006 Corrections required per Brandon Wright.. Complete list of repairs per Carlos Robles. |
City Development Engineer |
7/14/06 - Corrections required per Cathy H. Finish prepping roadbase.
9/28/06 Corrections required per Cathy H. 10% warranty bond. Electronic dwg of record. Rockwall certification.
10/27/06 Approved per Cathy H. |
Landscaping |
10/27/06 Approved per Cathy H. |
FINAL INSPECTION RELEASE APPROVALS |
Power |
12/11/06 Approved per Dennis Wright
01/03/2008 Approved per Dennis Wright.. 1 yr warranty |
Water |
12/12/06 Corrections required per Tim Dotson - Locate wire needs to be in working order.
1/8/07 Corrections required per Tim Dotson - Need to fix wire.
2/5/07 Approved per Wayne McIntosh - Wire is fixed. Painted fire hydrant and cut arrows in valve collars.
1/8/2008 Approved per Wayne M.. 1 yr warranty.. Checked all locate wire, located good |
Wastewater |
12/12/06 Corrections required per Tim Dotson - Locate wire needs to be in working order.
1/8/07 Corrections required per Tim Dotson - Need to fix wire.
2/5/07 Approved per Wayne McIntosh - Wire is fixed. Painted fire hydrant and cut arrows in valve collars.
1/8/2008 Approved per Wayne M.. 1 yr warranty.. Checked all locate wire, located good |
Engineering |
12/20/06 Approved per Carlos R
10/23/2008 Approved per Carlos Robles 1 yr warranty |
City Development Engineer |
12/10/2006 COrrections required per Ken Bricker.. General cleanup needed, building materials in gutter and laying on sidewalk..x-joints left in sidewalks-non-uniform, concrete collars are still under construction,dirt berms present at gutter
12/26/2006 Approved per Ken Bricker
1/4/08 - 1 year warranty - Approved Per Ken B - No corrections found. |
Landscaping |
12/10/2006 Approved per Ken Bricker.. No Landscaping present
1/4/08 - 1 year warranty - Approved Per Ken B - No corrections found. |
| |
General Comments: |
|