Drawing of Record Submitted |
12/21/2005 |
Electronic Drawing |
12/21/2005 |
Final Grading Report |
12/21/2005 |
Date Scheduled |
12/28/2005 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
01/03/2006 Approved per Dennis Wright
12/5/06 1 year warranty Approved per Dennis Wright. |
Water |
01/03/2006 Corrections required per Tim Jones..Hydrant needs to be painted. no backflow inspection tag, Needs W cut in curb for water meter, need inspection paperwork on double check on fire system.
01/06/2006 Approved Per Tim Jones.. per phone call @ 3:00 pm
2/27/07 1 year warranty - Approved per Darrin Judd. Wire okay. |
Wastewater |
01/03/2006 Corrections required per Tim Jones..Hydrant needs to be painted. no backflow inspection tag, Needs W cut in curb for water meter, need inspection paperwork on double check on fire system.
01/06/2006 Approved Per Tim Jones.. per phone call @ 3:00 pm
2/27/07 1 year warranty - Approved per Darrin Judd. Wire okay. |
Engineering |
12/28/2005 Approved per Larry Henderson |
City Development Engineer |
01/06/2005 Approved per Cathy H. Place rock at drain on South curb,/ place 3/4" gravel along East parking area to drain to the South.
12/26/2006 Approved per Cathy H.. 1 year warranty |
Landscaping |
01/05/2006 Corrections required per Ray Snyder.. Parking lot has not been installed per approved plan..
01/12/2006 Approved per Ray Snyder
12/26/2006 Approved per Cathy H. 1 year warranty |
| |
General Comments: |
|