Drawing of Record Submitted |
02/08/2006 |
Electronic Drawing |
02/09/2006 |
Final Grading Report |
02/23/2006..03/08/2006 revised |
Date Scheduled |
02/02/2006 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
03/01/2006 Approved per Dennis Wright
2/7/07 - 1 year warranty - Approved per Dennis Wright |
Water |
03/08/2006 Corrections required per Kevin Condie.. 1. Clean and paint Fire hydrant. 2. Could not meter setter for lot #14.
03/22/2006 Approved per Kevin Condie
2/27/07 1 year warranty - Approved per Darrin Judd. Wire okay. Meter boxes okay. |
Wastewater |
03/08/2006 Corrections required per Kevin Condie.. 1. Clean and paint Fire hydrant. 2. Could not meter setter for lot #14.
03/22/2006 Approved per Kevin Condie
2/27/07 1 year warranty - Approved per Darrin Judd. Wire okay. Meter boxes okay. |
Engineering |
03/02/2006 Corrections required per Larry Henderson.. Correct grading report,Clean gutters, replace curb section(2),verify capacity of detenetion basin, replace broken crub
03/21/2006 Corrections required per Carlos Robles.. Replace curb sections(Gutter), remove ramp
03/30/2006 Approved per Carlos Robles |
City Development Engineer |
03/17/2006 Corrections required per Jay Sandberg.. Need easement for drainage from SE corner of project. Driveway corrected at entrance as discussed.
03/24/2006 Corrections required per Jay Sandberg..Need copy of easement from detention pond east to street, need private improvement certifiication from engineer.
03/30/2006 Approved per Jay Sandberg.. PI certification ok, electronic drawing of record ok, easement to east for drainage recorded.
02/15/2007 Approved per Ken Bricker.. 1 year warranty |
Landscaping |
03/02/2006 Approved per Jay Sandberg
02/15/2007 Approved per Ken Bricker.. 1 year warranty |
| |