Drawing of Record Submitted |
02/27/2006..revised 03/16/2006 |
Electronic Drawing |
02/27/2006..revised 03/16/2006 |
Final Grading Report |
02/27/2006 |
Date Scheduled |
02/27/2006 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
02/27/2006 Approved per Dennis Wright |
Water |
02/27/2006 Corrections required per Kevin Condie..1. Need to concrete valves 2. Flush and check chlorine on fire line. 3. Test backflow on landscaping. 4. Need to check wire. |
Wastewater |
02/27/2006 Corrections required per Kevin Condie..1. Need to concrete valves 2. Flush and check chlorine on fire line. 3. Test backflow on landscaping. 4. Need to check wire. |
Engineering |
03/01/2006 Approved per Larry Henderson |
City Development Engineer |
03/03/2006 Approved 1. Electronic Dwg of record-need storm drain line size & slope, provide ties to sewer lateral locations(one from TBC and Corner of Bldg.) Send to [email protected] when revised. |
Landscaping |
02/27/2006 Corrections required per Ray Snyder.. 1. Complete landscaping ( or provide copy of invoice with surety.)2. Complete trash enclouse with solid metal gate( or provide copy of quote with surety.)3. Complete parking lot striping. 4. Complete sidewalks. |
| |
General Comments: |
|