| Drawing of Record Submitted | |
|---|---|
| Electronic Drawing | |
| Final Grading Report | |
| Date Scheduled | |
| BUILDING PERMIT RELEASE APPROVALS | |
| Power | |
| Water | |
| Wastewater | |
| Engineering | |
| City Development Engineer | |
| Landscaping | |
| FINAL INSPECTION RELEASE APPROVALS | |
| Power | 05/03/2006 Corrections required per Dennis Wright. No Utilities placed for all lots at this time. 09/01/2006 Approved per Dennis Wright.. Power installed no other development done. 12/10/2007 Approved per Dennis Wright.. 1 yr warranty |
| Water | 1/3/07 Approved with conditions per Tim Dotson - lot 1 okay. Lots 2 and 3 to be improved by owners (Received by Cathy H). Prior to CO on lot 1 - setter/meter must be collared per St George Specs. 12/11/2007 Approved per Tim Dotson 1 yr warranty |
| Wastewater | 1/3/07 Approved with conditions per Tim Dotson - lot 1 okay. Lots 2 and 3 to be improved by owners (Received by Cathy H). Prior to CO on lot 1 - setter/meter must be collared per St George Specs. 12/11/2007 Approved per Tim Dotson 1 yr warranty |
| Engineering | 1/3/07 Approved per Carlos R. 12/17/2007 Approved per Calros Robles 1yr warranty |
| City Development Engineer | 5/4/06 - Corrections REQUIRED per Wes Jenkins - complete improvements per plan. 9/29/06 Corrections Required per Cathy H. Requires letter from owner of lots 2 & 3 on utility installation. 1/2/07 Approved per Cathy H . Received recorded letter - owners to make utility improvements 12/12/07 - 1 year warranty - approved per Ken B. |
| Landscaping | 05/02/2006 Approved per Mark Bradley..N/A 12/12/07 - 1 year warranty - approved per Ken B. |
| General Comments: | |