Drawing of Record Submitted |
05/10/2006 |
Electronic Drawing |
05/05/2006 |
Final Grading Report |
05/05/2006 |
Date Scheduled |
05/15/2006 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
|
Water |
05/19/2006 Corrections required per Tim Dotson.. Need to pour concrete around meter box. 5/26/06 Corrections Required per Tim Dotson - Need lid on meter box. 5/30/06 Approved per Tim Dotson
04/30/2007 Approved per Kevin Condie.. 1 year warranty |
Wastewater |
05/19/2006 Corrections required per Tim Dotson.. Need to pour concrete around meter box. 5/26/06 Corrections Required per Tim Dotson - Need lid on meter box. 5/30/06 Approved per Tim Dotson
04/30/2007 Approved per Kevin Condie.. 1 year warranty |
Engineering |
05/17/2006 Corrections required per Carlos Robles..Light poles, detention basin, Driveway approach not as per plans.
05/26/2006 Approved per Carlos Robles.. South Driveway approach not as per plans |
City Development Engineer |
4/13/07 - 1 year warranty - per Cathy H. Private parking lot - NA for inspection. |
Landscaping |
5/24/06 Approved per Jay Sandberg
4/13/07 - 1 year warranty - per Cathy H. Private parking lot - NA for inspection. |
| |
General Comments: |
|