Drawing of Record Submitted |
08/10/2006..revised 8-18-06 |
Electronic Drawing |
08/10/2006..revised 8-18-06 |
Final Grading Report |
08/10/2006 |
Date Scheduled |
08/16/2006 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
08/18/2006 Approved Per Dennis W
8/3/07 - 1 year warranty - approved per Dennis Wright. |
Water |
08/18/2006 Approved per Tim Dotson
8/8/2007 1 yr warranty approved per Carson Tait |
Wastewater |
08/18/2006 Approved per Tim Dotson
8/8/2007 1 yr warranty approved per Carson Tait |
Engineering |
08/24/2006 Approved per Carlos Robles
8/13/2007 Approved per Carlos Robles.. 1 yr warranty |
City Development Engineer |
08/17/2006 Corrections required per Ken B. Materials on KVA transformer,solid metal gates are missing on trash enclosure,trash in parking lot area no ADA route to building present, Ada signage missing, 18"Corr. pipe present in parking lot area (Hole in asphalt).
8/22/06 Corrections required per Ken B. Enclosed dumpster missing gates, curbing laying in parking area, trash in parking area corner, no parking striping, ADA access route remains unmarked. Construction materials laying in gutter at the street.
8/24/06 Approved per Ken B.
8/6/07 - 1 year warranty - NA - private streets - per Cathy H. |
Landscaping |
08/17/2006 Corrections required per Ken B..Finish landscaping at street front.
8/22/06 Approved per Ken required per Ken B. Landscape rocks are missing at front by street. OK if area is only 10'x4' by North side of access per Cathy H..
8/6/07 - 1 year warranty - NA - private streets - per Cathy H. |
| |
General Comments: |
|