Drawing of Record Submitted |
2/2/2006 |
Electronic Drawing |
2/2/2006 |
Final Grading Report |
2/2/2006 |
Date Scheduled |
For Permits ONLY-09/25/2006 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
9/22/06 Approved phase ii per Dennis Wright |
Water |
9/29/06 Corrections required per Kevin Condie. They do not have high pressure line in. |
Wastewater |
9/29/06 Corrections required per Kevin Condie. They do not have high pressure line in. |
Engineering |
9/22/06 Approved Phase II per Brandon Wright |
City Development Engineer |
9/25/06 Approved phase II per Cathy H. |
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
12/8/06 Approved per Dennis Wright.
12/10/2007 Approved per Dennis Wright 1 yr warranty |
Water |
12/21/06 Corrections required per Kevin Condie. Need a record of drawing that is right.
1/5/07 Approved per Kevin C.
12/11/2007 Approved per Wayne M.. 1 yr warranty.. checked locate wire it is good. |
Wastewater |
12/21/06 Corrections required per Kevin Condie. Need a record of drawing that is right.
1/5/07 Approved per Kevin C.
12/11/2007 Approved per Wayne M.. 1 yr warranty.. checked locate wire it is good. |
Engineering |
12/20/06 Approved per Brandon W.
12/13/2007 Corrections required per Brandon Wright..1 yr warranty.. broken curb,street signs not in sunk water boxes(broken) |
City Development Engineer |
12/20/06 Corrections required per Cathy H. Electronic Dwg of record - still need update.
1/8/07 Approved per Cathy H.
12/12/07 - 1 year warranty - approved per Ken B. |
Landscaping |
12/12/07 - 1 year warranty - approved per Ken B. |
| |
General Comments: |
|