Drawing of Record Submitted |
10/19/2006..11/29/2006..revised.. 12/20/2006 |
Electronic Drawing |
10/19/2006..11/28/2006 |
Final Grading Report |
11/14/2006 |
Date Scheduled |
11/15/2006 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
11/15/06 Corrections required per Dennis Wright -- 600 amp on bldg A impacts show only 400 amps paid for.
11/20/2006 Approved per Dennis Wright |
Water |
11/15/06 Corrections required per Tim Dotson - As builts need corrections.
11/28/2006 Approved per Kevin Condie |
Wastewater |
11/15/06 Corrections required per Tim Dotson - As builts need corrections.
11/28/2006 Approved per Kevin Condie |
Engineering |
11/29/2006 Approved per Carlos Robles.. Note: Catch Basin needs to be fix and Engineer letter for it. |
City Development Engineer |
11/16/06 Approved per Ken B. |
Landscaping |
11/16/06 Corrections Required per Ken B - Landscape incomplete.
11/22/06 Approved per Ken B. |
| |
General Comments: |
|