| Drawing of Record Submitted | 10/19/2006..11/29/2006..revised.. 12/20/2006 |
|---|---|
| Electronic Drawing | 10/19/2006..11/28/2006 |
| Final Grading Report | 11/14/2006 |
| Date Scheduled | 11/15/2006 |
| BUILDING PERMIT RELEASE APPROVALS | |
| Power | |
| Water | |
| Wastewater | |
| Engineering | |
| City Development Engineer | |
| Landscaping | |
| FINAL INSPECTION RELEASE APPROVALS | |
| Power | 11/15/06 Corrections required per Dennis Wright -- 600 amp on bldg A impacts show only 400 amps paid for. 11/20/2006 Approved per Dennis Wright |
| Water | 11/15/06 Corrections required per Tim Dotson - As builts need corrections. 11/28/2006 Approved per Kevin Condie |
| Wastewater | 11/15/06 Corrections required per Tim Dotson - As builts need corrections. 11/28/2006 Approved per Kevin Condie |
| Engineering | 11/29/2006 Approved per Carlos Robles.. Note: Catch Basin needs to be fix and Engineer letter for it. |
| City Development Engineer | 11/16/06 Approved per Ken B. |
| Landscaping | 11/16/06 Corrections Required per Ken B - Landscape incomplete. 11/22/06 Approved per Ken B. |
| General Comments: | |