Drawing of Record Submitted |
11/06/2006 |
Electronic Drawing |
11/06/2006 |
Final Grading Report |
11/09/2006 |
Date Scheduled |
11/08/2006 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
|
Water |
11/9/06 Approved Per Tim Dotson.
11/14/2007 Approved per Darrin Judd..1 year warranty |
Wastewater |
11/9/06 Approved Per Tim Dotson.
11/14/2007 Approved per Darrin Judd..1 year warranty |
Engineering |
11/15/2006 Approved per Carlos Robles
11/08/2007 Approved per Brandon Wright.. 1 year warranty |
City Development Engineer |
11/9/06 Approved per Jay Sandberg. Discussed fire hydrant with Fire Chief. Discussed rail missing with Bldg offical.
11/5/07 - 1 year warranty - N/A per Cathy H. - Private parking lot. |
Landscaping |
11/9/06 Approved per Jay Sandberg.
11/5/07 - 1 year warranty - N/A per Cathy H. - Private parking lot. |
| |
General Comments: |
|