[Green Valley LDS 3rd Ward]
Number: Grading-38383

Drawing of Record Submitted 1/03/08..revised 1/17/2008
Electronic Drawing 1/03/08..revised 1/17/2008
Final Grading Report 1/10/2008
Date Scheduled 01/07/2008
BUILDING PERMIT RELEASE APPROVALS
Power
Water
Wastewater
Engineering
City Development Engineer
Landscaping
FINAL INSPECTION RELEASE APPROVALS
Power 1/08/2008 Approved per Dennis Wright 12/04/2008 Approved per Dennis Wright.. 1 year warranty
Water 1/8/2008 Corrections required Per Wayne M.. Need concrete around valve cans and arrows with pipe size cut in. Back flow need to have cert for Irr and Fire system. Paint Fire Hydrant down to the bottom of the concrete. Need to check locate wire. Need to lower Fie Hydrant need 8" of concrete around meter box and put rebar in the box. (Section 3.6.6.5 on Fire Hyd Spec) 1/15/2008 Approved per Wayne M 12/17/08 - 1 year warranty - approved per Daren Judd - Wire good.
Wastewater 1/8/2008 Corrections required Per Wayne M.. Need concrete around valve cans and arrows with pipe size cut in. Back flow need to have cert for Irr and Fire system. Paint Fire Hydrant down to the bottom of the concrete. Need to check locate wire. Need to lower Fie Hydrant need 8" of concrete around meter box and put rebar in the box. (Section 3.6.6.5 on Fire Hyd Spec) 1/15/2008 Approved per Wayne M 12/17/08 - 1 year warranty - approved per Daren Judd - Wire good.
Engineering 1/7/2008 Corrections required per Brandon Wright..Landscaping not complete,have not received Final Grading Report,show dentention basin on Drawing of Record,patch sidewalk and curb,lids on drain box & sidewalk,clean detention box and trough. 1/14/2008 Corrections required per Brandon Wright.. List not complete 1/18/2008 Approved per Brandon Wright 12/08/2008 Approved per Brandon Wright.. 1 year warranty
City Development Engineer 1/7/08 corrections required per Cathy H. Electronic DWG of record needs to show drainage improvements (location of holes in wall between church and homes, detention area and outlet structure etc). Per Ken B. Construction still in process. 1/14/08 corrections required per Ken B. Still installing landscape. 1/18/2008 Approved per Cathy H..Bond in place for landscaping 12/3/08 - 1 year warranty - just public roadway improvements - Approved per Ken B.
Landscaping 1/7/08 corrections required per Ken B. Construction still in process. 1/14/08 corrections required per Ken B. Still installing landscape. 1/18/2008 Approved per Cathy H.. Bond in place for landscaping 11/08/2008 Approved per Larry Shane.. 1 year warranty
    
General Comments: