Drawing of Record Submitted |
9/7/2007 |
Electronic Drawing |
9/7/2007 |
Final Grading Report |
9/7/2007..9/14/2007revised |
Date Scheduled |
9/11/2007 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
9/12/2007 Approved per Dennsi Wright
8/5/2008 Approved per Dennis Wright.. 1yr warranty |
Water |
9/11/2007 Corrections required per Kevin Condie.. make arrow bigger in concrete collars, clean and paint hydrants from top to concrete, no water at lot #47 & #48 corp must be off, meter setter need to be cleaned out has rock in it. lot #52. remove stress on sides of meter boxs,turn on all valves, Irrigation meter box need concrete w/rebar.
9/14/2007 Approved per Kevin Condie
8/28/2008 Approved per Kevin Condie.. 1yr warranty.. wire good |
Wastewater |
9/11/2007 Corrections required per Kevin Condie.. make arrow bigger in concrete collars, clean and paint hydrants from top to concrete, no water at lot #47 & #48 corp must be off, meter setter need to be cleaned out has rock in it. lot #52. remove stress on sides of meter boxs,turn on all valves, Irrigation meter box need concrete w/rebar.
9/14/2007 Approved per Kevin Condie
8/28/2008 Approved per Kevin Condie.. 1yr warranty.. wire good |
Engineering |
9/12/2007 Corrections required per Brandon Wright.. Grading report does not meet City Spec. broken walk and gutter needs repair.
9/18/2007 Approved per Brandon Wright
8/6/08 - 1 year warranty - Corrections required per Brandon W. Remove dirt of sidewalk on Sir Monte. |
City Development Engineer |
9/10/07 corrections required per Cathy H. Electronic dwg of record needs to show a tie also from sewer MH to lateral. The storm drain pipe needs to be labeled with size, type and length. Need to include actual as-built pts in dwg. Elec dwg needs to be put into city HCN (off to the North). Need timeframe for removal of excess material.
9/19/07 corrections required per Cathy H. 10% warranty bond. Landscape bond 120%. per Ken B. No landscape present, silt fence is still up.
9/28/07 approved per Cathy H.
8/5/08 - 1 year warranty - Check public street only (Sir Monte Drive) - Approved per Ken B. |
Landscaping |
9/10/07 corrections required per Cathy H. Need bond for landscaping. per Ken B. No landscape present, still grading, heavy equipment still on site, trash dumpster on site, silt fence is still up.
9/19/07 corrections required per Cathy H. 10% warranty bond. Landscape bond 120%. per Ken B. No landscape present, silt fence is still up.
9/28/07 approved per Cathy H.
8/5/08 - 1 year warranty - Check public street only (Sir Monte Drive) - Approved per Ken B. |
| |
General Comments: |
|