Drawing of Record Submitted |
05/12/2003, 05/28/2003 |
Electronic Drawing |
|
Final Grading Report |
05/12/2003 |
Date Scheduled |
|
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
|
Water |
5/16/2003. Corrections needed per Kevin
Meter boxes w/rc on them remove concrete form box
raise to meter betters
clean one meter box
clean hydrant & paint if needed
06/12/2003. approved per Kevin
09/08/2003. approved per Jeff Lance.
06/11/2003. Approved per Kevin Condie
Approved per Kevin Condie
06/11/2003.approved per Kevin Condie
need to find old service on 2450 So &
remove meter & abondon at main
06/06/2003. approved per Kevin
on as built wc need to show how water goes under 18" line in 2450 So
Stub lines need (apor plug put on them) |
Wastewater |
5/16/2003. Corrections needed per Kevin
Meter boxes w/rc on them remove concrete form box
raise to meter betters
clean one meter box
clean hydrant & paint if needed
06/12/2003. approved per Kevin
09/08/2003. approved per Jeff Lance.
06/11/2003. Approved per Kevin Condie
Approved per Kevin Condie
06/11/2003.approved per Kevin Condie
need to find old service on 2450 So &
remove meter & abondon at main
06/06/2003. approved per Kevin
on as built wc need to show how water goes under 18" line in 2450 So
Stub lines need (apor plug put on them) |
Engineering |
05/13/2003 Corrections required per Larry Henderson
trim expansion joints
sight distance onto 2450 so blocked by walls, east & west
install street lights
06/17/2003. Approved per Cathie Hasfurther.
06/17/2003. Approved per Mike Hester
05/29/2003. Corrections requiredPer Mike Heston 1. Clean the public improvements 2. use two chevrons and paint the closing tapon on 2450 South. 3. Place rip rap at the S.D. outlet. 4. Complete the electrical. 5. Backfill all sidewalks.
ramp ends of sidewalk
complete paving on west end of 2450 so
reset lot corners
remove dirt ramp on westside of 2160 so
remove boards from gutter on 2160 E& 2450 So
shoulder asphalt taper on 2450 So.
backfill trench on So. side of 2450 So(safety hazzard)
complete landscaping on 2450 So. holes are safety hazzard -more items may be added-
set section cornor per City Surveyer
5-13-03
9/2/2003. Corrections Required per Mike hester. Install all property ?corners. Backfill all sidewalks; replace damaged ADA ramp as marked in phase I and side walk. Grout under the street light bars. Clean all storm drain boxes and remove excess concrete around the pipes. Recompact the sink hole and repair the asphalt on the n/w storm box on 2660 S. finish the dentintion basion. Fix the "BIG HOLE" in the pavement.
09/09/2003. Approved per Mike Hester. |
City Development Engineer |
05/14/2003 Corrections Required per Cathie Hasfurther
Need electronic drawing of record
11/25/03. Approved per Cathy. |
Landscaping |
05/16/2003. Correction required per Mark Bradley Trees need to be installed.
05/20/2003.Approved for Trees only per Matt Callister, further approval in needed for City Maintence of row landscaping. *Why is row landscarpe strip less then four feet?
8/29/2003. APPROVED per Mark Bradley |
| |
General Comments: |
|