| Drawing of Record Submitted | 7/16/2007 |
|---|---|
| Electronic Drawing | 7/16/2007 |
| Final Grading Report | 8/9/2007 revised |
| Date Scheduled | |
| BUILDING PERMIT RELEASE APPROVALS | |
| Power | |
| Water | |
| Wastewater | |
| Engineering | |
| City Development Engineer | |
| Landscaping | |
| FINAL INSPECTION RELEASE APPROVALS | |
| Power | |
| Water | 7/26/2007..corrections required per Carson Tait.. The backflow assembly needs to be raised. The installation criteria for a pub states that it is to be installed 12" above the highest outlet. It also needs to be tested and tagged after it has been installed correctly. 7/31/07 corrections required per Darrin Judd - PVB not 12" above highest outlet. Also needs to be tested and tagged. 8/17/2007 Approved per Carson Tait |
| Wastewater | 7/26/2007..corrections required per Carson Tait.. The backflow assembly needs to be raised. The installation criteria for a pub states that it is to be installed 12" above the highest outlet. It also needs to be tested and tagged after it has been installed correctly. 7/31/07 corrections required per Darrin Judd - PVB not 12" above highest outlet. Also needs to be tested and tagged. 8/17/2007 Approved per Carson Tait |
| Engineering | 7/30/2007 Corrections required per Brandon Wirght.. No grading report on testing 8/9/2007 Approved per Brandon W. |
| City Development Engineer | Corrections required per Cathy H...Provide Elec drawing of record in Autocad format, showing all utilities,dimensions, location, etc. 7/26/07 corrections required per Cathy H. Electronic dwg of record needs to be put on city HCN system. |
| Landscaping | 7/26/07 approved per Ken B. |
| General Comments: | |