| Drawing of Record Submitted | 7/2/2007..revised 7/16/2007 |
|---|---|
| Electronic Drawing | 7/3/2007..revised 7/16/2007 |
| Final Grading Report | 7/6/2007 |
| Date Scheduled | 7/10/2007 |
| BUILDING PERMIT RELEASE APPROVALS | |
| Power | |
| Water | |
| Wastewater | |
| Engineering | |
| City Development Engineer | |
| Landscaping | |
| FINAL INSPECTION RELEASE APPROVALS | |
| Power | 7/10/2007 Approved per Dennis Wright 6/3/2008 Apporved per Dennis Wright.. 1 yr warranty |
| Water | 7/12/07 Corrections required per Carson Tait 7/13/2007 Approved per Carson Tait 6/13/08 - 1 year warranty - approved per Carson Tait. Wire Good. |
| Wastewater | 7/12/07 Corrections required per Carson Tait 7/13/2007 Approved per Carson Tait 6/13/08 - 1 year warranty - approved per Carson Tait. Wire Good. |
| Engineering | 7/11/07 approved per Carlos R. 6/24/2008 Approved per Carlos Robles 1 yr warranty |
| City Development Engineer | 7/10/07 corrections required per Ken B. Fire hydrant pad not poured. 7/12/07 approved per Cathy H. 6/10/08 - 1 year warranty - approved per Ken B. |
| Landscaping | 7/10/07 corrections required per Ken B. Landscape incomplete at fire hydrant in frontage. 7/12/07 approved per Cathy H.6/10/08 - 1 year warranty - approved per Ken B. |
| General Comments: | |