Drawing of Record Submitted |
2/9/2009 |
Electronic Drawing |
2/9/2009 |
Final Grading Report |
2/9/2009 |
Date Scheduled |
2/10/2009 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
2/17/2009 Approved per Dennis Wright
1/28/2010 Approved per Dennis Wright.. 1 year warranty |
Water |
2/9/2009 Approved per Kevin Condie
2/1/10 - 1 year warranty - CORRECTIONS REQUIRED per Kevin C. May have water or storm drain leak. (2) sidewalk areas are dropped by meter boxes.
2/11/2011 Approved per Kevin Condie.. 1 year warranty |
Wastewater |
2/9/2009 Approved per Kevin Condie
2/1/10 - 1 year warranty - CORRECTIONS REQUIRED per Kevin C. May have water or storm drain leak. (2) sidewalk areas are dropped by meter boxes.
2/11/2011 Approved per Kevin Condie.. 1 year warranty |
Engineering |
2/10/2009 Corrections required per Brandon Wright.. Monuments not in and stamped, finish rock walls per plan
2/1/10 - 1 year warranty - CORRECTIONS REQUIRED per Brandon W. Pads need to be finished. Rock walls need to be finished. Road failing.
2/11/2011 Approved per Brandon Wright.. 1 year warranty |
City Development Engineer |
2/10/2009 Corrections required per Cathy H.. 1. 10% Warranty Bond, 2. rock wall certifications, 3. Electronic Dwg of record need to show all walls in developemnt as-constructed.
2/1/10 - 1 year warranty - CORRECTIONS REQUIRED per Cathy H. Pads need to be finished. Rock walls need to be finished. Road failing.
2/14/2011 Approved per Brett Bingham.. 1 year warranty |
Landscaping |
2/9/2009 Approved per Larry Shane
2/1/10 - 1 year warranty - approved per Ken B. |
| |
General Comments: |
|