[Bloomington Courtyard-Mediacl Bldg # F]
Number: Grading-34806

Drawing of Record Submitted 7/31/2007.revised 8-7-2007
Electronic Drawing 7/31/2007 e-mailed
Final Grading Report 7/31/2007
Date Scheduled 8/2/2007
BUILDING PERMIT RELEASE APPROVALS
Power
Water
Wastewater
Engineering
City Development Engineer
Landscaping
FINAL INSPECTION RELEASE APPROVALS
Power
Water 8/3/07 corrections required per Kevin C. Valve in Young street 2710 need to be concreted in. Test backflow on fire sprinkler system. No concrete around fire hydrant and meter. 8/9/2007 Approved per Darren Judd 7/14/2008.. 1yr warranty..Wire good-TD
Wastewater 8/3/07 corrections required per Kevin C. Valve in Young street 2710 need to be concreted in. Test backflow on fire sprinkler system. No concrete around fire hydrant and meter. 8/9/2007 Approved per Darren Judd 7/14/2008.. 1yr warranty..Wire good-TD
Engineering 8/8/2007 Approved per Carlos/Cathy H.. Warranty Bond w/Bob N. 7/9/2008 Approved per Brandon Wright.. 1 year warranty
City Development Engineer 8/2/07 corrections required per Cathy H. Electronic DWG of record needs to be placed in city HCN system. per Ken B. Dumpster and port-a-pot still on site. Fire hydrants missing pads. Dirt berms present. Construction still in progress. Asphalt spauling in parking lot. No signage. 8/9/2007 Corrections required per Ken/Jay S..Large holes in privacy wall.Trench still open at frontage,dirt berm present landscape is incomplete,sidewak needs R/R,curb needs R/R, privacy wall is incomplete.Replace sidewalk 7 sections. 8/13/2007 Approved per Jay Sandberg 7/7/08 - 1 year warranty - private improvements only - approved per Cathy H.
Landscaping 8/2/07 corrections required per Ken B. Dumpster and port-a-pot still on site. Fire hydrants missing pads. Dirt berms present. Construction still in progress. Asphalt spauling in parking lot. No signage. 8/9/2007 Approved per Ken B 7/7/08 - 1 year warranty - private improvements only - approved per Cathy H.
    
General Comments: