[Taipan Trading]
Number: Grading-38772

Drawing of Record Submitted 10/30/2007
Electronic Drawing 10/30/2007
Final Grading Report 11/29/2007
Date Scheduled 11/01/2007
BUILDING PERMIT RELEASE APPROVALS
Power
Water
Wastewater
Engineering
City Development Engineer
Landscaping
FINAL INSPECTION RELEASE APPROVALS
Power 10/31/2007 Approved per Dennis Wright 11/04/2008 Approved per Dennis Wright 1 yr warranty
Water 11/07/2007 Corrections per Darrin Judd.. Need to uncover valve can lid on hydrant on Southeast corner of project. backflow assembly needs to be tested and tagged. Arrows add line size need to be cut on concrete at T on the Northwest side of project. 12/11/2007 Approved per Carson Tait 11/13/2008 Approved per Carson Tait..1 year warranty.. wire good
Wastewater 11/07/2007 Corrections per Darrin Judd.. Need to uncover valve can lid on hydrant on Southeast corner of project. backflow assembly needs to be tested and tagged. Arrows add line size need to be cut on concrete at T on the Northwest side of project. 12/11/2007 Approved per Carson Tait 11/13/2008 Approved per Carson Tait..1 year warranty.. wire good
Engineering 11/01/2007 Approved per Carlos Robles.. 2 Year warratny required on South frontage road landscaping not completed. 4/2/09 - 1 year warranty - approved per Carlos R.
City Development Engineer 10/31/2007 Corrections required per Ken Bricker.. Construction still in process,safety fence is needed at frontage wall(one to drop off)No doors/gates on trash enecloure guards are needed at front detention areas,landscape still be installed. 11/6/07 corrections required per Cathy H. Electronic dwg of record needs to show all drainage improvements and detention basin locations with capacity on site (TaiPan). 11/30/2007 Corrections required per Cathy H.1. See previous comments from 10-31-07 for Electronic Dwg of Record. Needs storm drain info. 2. Drainage along 850 North at East end needs to be addressed. 3.End of Road markers needed at far Southeast corner of parking lot, construction mat'l. at back of building.4. Trash enclosure is missing solid metal door 5. Guards are needed at front detention areas(driving hazard). 6. End road markers needed at front accesses. 7. Resolve slopes and steepness of detention basin.(Safety Hazard). Approved per Cathy H..Add end of Road markers on East ans South side of South East side of parking lot. 11/4/08 - 1 year warranty - approved per Ken B.
Landscaping 10/31/2007 Corrections required per Ken Bricker.. Construction still in process safety fence is needed at Frontage wall(one to drop off)No doors/gates on trash enclosure.guards are needed at front detention areas, landscape still be installed. 11/30/2007 Corrections per Cathy H.1. See previous comments from 10-31-07 for Electronic Dwg of Record. Needs storm drain info. 2. Drainage along 850 North at East end needs to be addressed. 3.End of Road markers needed at far Southeast corner of parking lot, construction mat'l. at back of building.4. Trash enclosure is missing solid metal door 5. Guards are needed at front detention areas(driving hazard). 6. End road markers needed at front accesses. 7. Resolve slopes and steepness of detention basin.(Safety Hazard). Approved per Cathy H..Add end of Road markers on East ans South side of South East side of parking lot. 11/19/2008 Approved per Larry Shane.. 1 year warranty
    
General Comments: