Drawing of Record Submitted |
4/3/2009 |
Electronic Drawing |
4/3/2009 |
Final Grading Report |
4/3/2009 |
Date Scheduled |
4/7/2009 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
|
Water |
4/9/2009 Approved per Carson Tait |
Wastewater |
4/9/2009 Approved per Carson Tait |
Engineering |
4/9/2009 Approved per Brandon Wright.. Note: Grading report not enough test taken on project. Drawing of record is not complete need to show all utilites and sizes. Dumpster enclousere not built at time of Final. to be delayed. |
City Development Engineer |
4/7/2009 Corrections required Per Cahty H..1. Missing stop sign 2. Missing trash enclosure 3. Missing parking stall striping at rear of bldg (5 stalls). 4. Detention is incomplete. 5. Elect Drawing of record require changes (sent to Horizon). 6.Asphalt in rear of building needs to be extended a minimum of 25' to accommodate 5 stalls and d drive aisle.
4/14/09 corrections required per Cathy H. Electronic DWG of Record OK. Parking of vehicles need to be on all weather surfacing (asphalt/concrete) - Code Section 10-19-8. Also, see previous list (1,2,3,4 and 6) - 1. Missing stop sign 2. Missing trash enclosure 3. Missing parking stall striping at rear of bldg (5 stalls). 4. Detention is incomplete. 6. Asphalt in rear of building needs to be extended a minimum of 25' to accommodate 5 stalls and d drive aisle. |
Landscaping |
4/8/2009 Approved per Larry Shane |
| |