Drawing of Record Submitted |
11/06/2007 |
Electronic Drawing |
11/06/2007 |
Final Grading Report |
11/10/2007 |
Date Scheduled |
11/12/2007 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
|
Water |
12/13/2007 Corrections required per Wayne M.. Meter box needs a new lid,the break a way on the fire hyd is below the concrete and the in line valve needs to be found and paint the Fire Hyd. |
Wastewater |
12/13/2007 Corrections required per Wayne M.. Meter box needs a new lid,the break a way on the fire hyd is below the concrete and the in line valve needs to be found and paint the Fire Hyd. |
Engineering |
12/13/2007 Approved per Carlos Robles |
City Development Engineer |
12/12/07 corrections required per Cathy H. Electronic DWG of record needs to be put into the city HCN system. Also all storm drain MH and inlet information needs to be provided. |
Landscaping |
12/12/07 approved per Cathy H. |
| |
General Comments: |
|