Drawing of Record Submitted |
9/19/2008..revised 9/29/08 |
Electronic Drawing |
9/19/2008..revised 9/29/08 |
Final Grading Report |
9/19/2008..revised 9/29/08 |
Date Scheduled |
9/22/2008 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
9/24/2008 Approved per Ron Terry
8/19/09 - 1 year warranty - approved per Dennis W. |
Water |
9/25/2008 Approved per Carson Tait
10/16/2009 Approved per Darrin Judd.. 1 year warranty wire good |
Wastewater |
9/25/2008 Approved per Carson Tait
10/16/2009 Approved per Darrin Judd.. 1 year warranty wire good |
Engineering |
9/24/2008 Approved per Carlos Robles
8/19/09 - 1 year warranty - approved per Brandon W. |
City Development Engineer |
9/22/08 corrections required per Cathy H. Electronic dwg of record needs to be surveyed for actual locations on as-builts. Utilities and grading need to be in same dwg. All lines, man holes, boxes, etc need to be labeled appropriately. Language of "to install" needs to be removed. per Ken B. Concrete collars are being installed at man holes, ext lighting is incomplete and electric at service islands still being installed.
9/29/08 approved per Cathy H.
8/20/09 - 1 year warranty - approved per Ken B. |
Landscaping |
9/22/08 approved per Cathy H.
8/20/09 - 1 year warranty - approved per Ken B. |
| |