| Drawing of Record Submitted | 5 copies 2/13/2008 |
|---|---|
| Electronic Drawing | 2/13/2008..revised 3/3/2008..revised 3/19/2008 |
| Final Grading Report | 2/13/2008..revised 3/3/2008..revised 3/19/2008 |
| Date Scheduled | 2/14/2008 |
| BUILDING PERMIT RELEASE APPROVALS | |
| Power | |
| Water | |
| Wastewater | |
| Engineering | |
| City Development Engineer | |
| Landscaping | |
| FINAL INSPECTION RELEASE APPROVALS | |
| Power | 2/26/2008 Corrections required per Dennis Wright.. Power not ready 3/3/2008 Approved per Dennis Wright 2/4/2009 Approved per Dennis Wright.. 1 year warranty |
| Water | 2/14/2008 Corrections required per Kevin Condie..Back flow on landscaping need to be tested. Landscape meter need a 1" meter box on it not 3/4 box. There are 5 or 6 meter pad dropping in the rear of pad Rhett will raise and fix them, if he can not fix, he will replace pads, wire ok as per Tim Datson 3/21/08 approved per Kevin Condie 2/17/2009 Approved per Kevin Condie.. 1 year warranty.. Wire good 2/13/09 |
| Wastewater | 2/14/2008 Corrections required per Kevin Condie..Back flow on landscaping need to be tested. Landscape meter need a 1" meter box on it not 3/4 box. There are 5 or 6 meter pad dropping in the rear of pad Rhett will raise and fix them, if he can not fix, he will replace pads, wire ok as per Tim Datson 3/21/08 approved per Kevin Condie 2/17/2009 Approved per Kevin Condie.. 1 year warranty.. Wire good 2/13/09 |
| Engineering | 2/15/08 corrections required per Brandon W. Street signs raised to 7' above walk. Move plants out of sight line. Monument on 740 S Cul de sac needs to be placed and stamped. Striping plan on Dixie Dr decel lane contact Jay Smith Streets Dept. 3/4/2008 Corrections required per Brandon Wright.. Drainage problem on lot#38 & 39 water standing on lot and in electric box, Erosion problems on slopes need some info from AGEC. 3/20/2008 Approved per Brandon Wright 2/5/09 - 1 year warranty - corrections required per Brandon W. Roads are splitting open along seams and trench lines. Asphalt spalding in cul-de-sac on 680 S. Curb and gutter and sidewalk moving away from asphalt and settling. 4/22/09 - 1 year warranty - approved per Brandon W. |
| City Development Engineer | 2/19/2008 Corrections required per Cathy H. Electronic Dwg of record- see comment on attached paper copy of Dwg of records. 3/3// Corrections required per Cathy H.. 10% warranty bond for public improvements Hillside compliance letter, Electronic Dwg of records needs to show, additional ground water drains discussed at mtg on 3-5-08 3/20/2008 Corections required per Cathy H.. 10% Warranty Bond, Hillside Compliance letter 3/21/08 approved per Cathy H 2/5/09 - 1 year warranty - approved per Ken B. |
| Landscaping | 2/19/2008 Corrections required per Ken Bricker.. All street lights missing(not installed yet) 3/3/2008 Corrections required per Ken Bricker ..10% warranty bond for public improvements Hillside compliance letter, Electronic Dwg of records needs to show, additional ground water drains discussed at mtg on 3-5-08 3/20/2008 Corrections required per Ken Bricker.. 10% Warranty Bond, Hillside Compliance letter 3/21/08 approved per Cathy H 2/6/2009 Approved per Shane Moore.. 1 year warranty |
| General Comments: | |