Drawing of Record Submitted |
9/24/2008..revised 10/14/08 |
Electronic Drawing |
9/25/2008..revised 10/14/08 |
Final Grading Report |
9/25/2008 |
Date Scheduled |
9/29/2008 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
9/30/2008 Approved per Dennis Wright
9/1/2009 Approved per Dennis Wright.. 1 year warranty |
Water |
10/03/2008 Corrections required per Per Darren Judd.. Back flow assemblies on fire risers and landscaping were to be tested and tagged,All valves need to be raised and collard valve in planter at end of Cul da sac needs to be raised. Meter boxes need to be cleaned out. Hydrant in middle of project needs to be poured. Contractor needs to shows that trace wire works.
10/27/2008 Approved per Darrin
10/16/2009 Approved per Darrin Judd.. 1 year warranty.. wire good |
Wastewater |
10/03/2008 Corrections required per Per Darren Judd.. Back flow assemblies on fire risers and landscaping were to be tested and tagged,All valves need to be raised and collard valve in planter at end of Cul da sac needs to be raised. Meter boxes need to be cleaned out. Hydrant in middle of project needs to be poured. Contractor needs to shows that trace wire works.
10/27/2008 Approved per Darrin
10/16/2009 Approved per Darrin Judd.. 1 year warranty.. wire good |
Engineering |
9/29/2008 Corrections required per Brandon Wright..Site is not landscaped, cannot find drain in sidewalk on plan remove,dumpster enclosure is not complete, need to remove all dumpsters and porta potty on site. Broken walk on Tonaquint Dr & gutter, drain under wall on Tonaquint Dr needs to be removed. Cannot drain out or City walk, landscape & rip rap detention pond.
10/28/2008 Approved per Brandon Wright
9/2/09 - 1 year warranty - approved per Brandon W. |
City Development Engineer |
9/29/08 corrections required per Cathy H. Electronic DWG of record - grading and utilities need to be all in one DWG (combine). Show sewer lateral ties from TBC to CO and bldg to CO. Is the sewer connected to city system (states by city - is it done?) Show detention facilities as constructed. What is purpose of curb opening on DWG? It is at the high point.
10/16/2008 Approved per Cathy Hasfurther
8/31/2009 Approved per Cathy H.. 1 year warranty Private improvements only |
Landscaping |
9/29/08 corrections required per Ken B. Still under construction with landscape incomplete.
10/16/2008 Corrections required per Ken Bricker.. Landscaping incomplete in front of units
10/27/2008 Approved per Ken Bricker
8/31/2009 Approved per Cathy H.. 1 year warranty Private improvements only |
| |
General Comments: |
|