Drawing of Record Submitted |
2/12/2009 |
Electronic Drawing |
2/12/2009 |
Final Grading Report |
2/12/2009 |
Date Scheduled |
2/17/2009 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
|
Water |
2/18/2009 Approved per Kevin Condie
1/13/2010 Approved per Tim Dotson.. 1 year warranty |
Wastewater |
2/18/2009 Approved per Kevin Condie
1/13/2010 Approved per Tim Dotson.. 1 year warranty |
Engineering |
2/19/2009 Corrections required per Brandon Wright..Stop signs need to be installed.
2/23/2009 Approved per Brandon Wright
1/6/10 - 1 year warranty - approved per Brandon W. |
City Development Engineer |
2/17/09 corrections required per Cathy H. Electronic DWG of Record OK. Missing stops signs at both exits. Tall boulders and trees in sight triangles. Slats in sliding gate.
2/23/2009 Corrections required per Ken Bricker.(Cathy H.) Large Boulders & trees in clear zone. Sight Dist areas. Note: Refer to approved plans *sheet L-1
3/2/09 approved per Cathy H.
1/4/10 - 1 year warranty - approved per Ken B. |
Landscaping |
2/20/2009 Approved per Laura Taylor
1/4/10 - 1 year warranty - approved per Ken B. |
| |
General Comments: |
|