[Desert Sands Phase IV]
Number: Grading 27443

Drawing of Record Submitted Received 11/18/03
Electronic Drawing 12/1/03
Final Grading Report
Date Scheduled
BUILDING PERMIT RELEASE APPROVALS
Power
Water 08/07/2003. Corrections required per Jeff Lance. Subdivison not ready. 8/21/03. pouring around valves raising valves. 8/22/03. No fire protection, system NOT APPROVED. Working on valve colors flushed out line need to do bactiria test monday 8/25/03. 8/26/03 -- Approved per jeff lance.
Wastewater 08/07/2003. Corrections required per Jeff Lance. Subdivison not ready. 8/21/03. pouring around valves raising valves. 8/22/03. No fire protection, system NOT APPROVED. Working on valve colors flushed out line need to do bactiria test monday 8/25/03. 8/26/03 -- Approved per jeff lance.
Engineering 07/31/2003. Corrections required per Mike Hester. Provide the interior grading report, complete all lot grading, construct south retaining wall, ripe rape the discharge pipe into the Ft. Prem. wash. 8/22/3003. APPROVED per Mike Hester.
City Development Engineer 8-5-03 Approved for pemits only - Jay Sandberg
Landscaping
FINAL INSPECTION RELEASE APPROVALS
Power
Water 11/19/2003 Correction required per Jeff Lance. Need to fix values on drawing of record. Need to clean all meter boxes and concrete. Meter pad and fire hydrant low. Lots 227, 226. Remove and repair concrete and raise to grade. Lot 274 setter needs to be moved back and put in center of box. fire hydrant needs concrete. Lots 219 and 220 remove concrete and replace to grade. Clean and bring up wire in lots 218 and 219 still need to checkwire. 11/21/03 corrections required per Jeff Lance. Not ready. 11/26/03. Approved per Jeff Lance
Wastewater 11/19/2003 Correction required per Jeff Lance. Need to fix values on drawing of record. Need to clean all meter boxes and concrete. Meter pad and fire hydrant low. Lots 227, 226. Remove and repair concrete and raise to grade. Lot 274 setter needs to be moved back and put in center of box. fire hydrant needs concrete. Lots 219 and 220 remove concrete and replace to grade. Clean and bring up wire in lots 218 and 219 still need to checkwire. 11/21/03 corrections required per Jeff Lance. Not ready. 11/26/03. Approved per Jeff Lance
Engineering 11/18/2003 Corrections required per Mike Hester. Provide the final grading and testing report. Provide the engineers Cirt. of Complinace. Install street name and traffic control signs. Make or comply with road improvements conditions on River Road. 11/21/03. Corrections required per Mike Hester. Not ready, must complete the punch list. 12/2/2003. Approved per Mike Hester
City Development Engineer 11/25/03. Corrections required per Jay Sandberg. Need electronic drawing of record. 12-01-03 Electronic Drawing of Record Submitted and approved Approved per Jay Sandberg
Landscaping
    
General Comments: