Drawing of Record Submitted |
Received 11/18/03 |
Electronic Drawing |
12/1/03 |
Final Grading Report |
|
Date Scheduled |
|
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
08/07/2003. Corrections required per Jeff Lance. Subdivison not ready.
8/21/03. pouring around valves raising valves.
8/22/03. No fire protection, system NOT APPROVED. Working on valve colors flushed out line need to do bactiria test monday 8/25/03.
8/26/03 -- Approved per jeff lance. |
Wastewater |
08/07/2003. Corrections required per Jeff Lance. Subdivison not ready.
8/21/03. pouring around valves raising valves.
8/22/03. No fire protection, system NOT APPROVED. Working on valve colors flushed out line need to do bactiria test monday 8/25/03.
8/26/03 -- Approved per jeff lance. |
Engineering |
07/31/2003. Corrections required per Mike Hester. Provide the interior grading report, complete all lot grading, construct south retaining wall, ripe rape the discharge pipe into the Ft. Prem. wash.
8/22/3003. APPROVED per Mike Hester. |
City Development Engineer |
8-5-03 Approved for pemits only - Jay Sandberg |
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
|
Water |
11/19/2003 Correction required per Jeff Lance. Need to fix values on drawing of record. Need to clean all meter boxes and concrete. Meter pad and fire hydrant low. Lots 227, 226. Remove and repair concrete and raise to grade. Lot 274 setter needs to be moved back and put in center of box. fire hydrant needs concrete. Lots 219 and 220 remove concrete and replace to grade. Clean and bring up wire in lots 218 and 219 still need to checkwire.
11/21/03 corrections required per Jeff Lance. Not ready.
11/26/03. Approved per Jeff Lance |
Wastewater |
11/19/2003 Correction required per Jeff Lance. Need to fix values on drawing of record. Need to clean all meter boxes and concrete. Meter pad and fire hydrant low. Lots 227, 226. Remove and repair concrete and raise to grade. Lot 274 setter needs to be moved back and put in center of box. fire hydrant needs concrete. Lots 219 and 220 remove concrete and replace to grade. Clean and bring up wire in lots 218 and 219 still need to checkwire.
11/21/03 corrections required per Jeff Lance. Not ready.
11/26/03. Approved per Jeff Lance |
Engineering |
11/18/2003 Corrections required per Mike Hester. Provide the final grading and testing report. Provide the engineers Cirt. of Complinace. Install street name and traffic control signs. Make or comply with road improvements conditions on River Road.
11/21/03. Corrections required per Mike Hester. Not ready, must complete the punch list.
12/2/2003. Approved per Mike Hester |
City Development Engineer |
11/25/03. Corrections required per Jay Sandberg. Need electronic drawing of record.
12-01-03 Electronic Drawing of Record Submitted and approved Approved per Jay Sandberg |
Landscaping |
|
| |
General Comments: |
|