Drawing of Record Submitted |
5/18/2009..revised 6/9/09 |
Electronic Drawing |
5/18/2209..revised 6/9/09 |
Final Grading Report |
5/15/2009 |
Date Scheduled |
5/18/2009 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
5/21/09 approved per Dennis W.
2/26/2010 Approved per Dennis Wright 1 year warranty |
Water |
5/21/09 correction required per Kevin C. Fire line needs to be cut off at valve and capped. Check backflow on Irr system.
5/26/2009 Corrections required per Carson Tait.. Need to have a concrete pad poured around the meter box. Need as as-built drawing.Need trhe hose bib cut off that is in the valve box
5/29/2009 Approved per Kevin Condie..per Phone Call @ 9:30
6/9/2009 Comments.. ok by Scott Taylor-concrete around meter box should have been done on Final of project & tap is a after back flow.
3/10/2010 Approved per Kevin Condie.. 1 year warranty |
Wastewater |
5/21/09 correction required per Kevin C. Fire line needs to be cut off at valve and capped. Check backflow on Irr system.
5/26/2009 Corrections required per Carson Tait.. Need to have a concrete pad poured around the meter box. Need as as-built drawing.Need trhe hose bib cut off that is in the valve box
5/29/2009 Approved per Kevin Condie..per Phone Call @ 9:30
6/9/2009 Comments.. ok by Scott Taylor-concrete around meter box should have been done on Final of project & tap is a after back flow.
3/10/2010 Approved per Kevin Condie.. 1 year warranty |
Engineering |
5/19/09 approved per Brandon W.
2/25/10 - 1 year warranty - Approved per Brandon W. |
City Development Engineer |
5/21/09 approved per Cathy H. Electronic DWG of record, okay.
2/25/10 - 1 year warranty - Just Check Landscaping - Approved per Ken B. |
Landscaping |
5/21/09 approved per Cathy H.
2/25/10 - 1 year warranty - Just Check Landscaping - Approved per Ken B. |
| |
General Comments: |
|