Drawing of Record Submitted |
11/07/2008..12/01/08 |
Electronic Drawing |
11/07/2008..12/01/08 |
Final Grading Report |
11/07/2008 |
Date Scheduled |
11/12/2008 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
11/12/2008 Approved per Dennis Wright
10/29/2009 Approved per Dennis Wright.. 1 year warranty |
Water |
11/17/2008 Approved per Carson Tait.. 11/13 wire good
12/4/09 - 1 year warranty - Approved per Kevin C. |
Wastewater |
11/17/2008 Approved per Carson Tait.. 11/13 wire good
12/4/09 - 1 year warranty - Approved per Kevin C. |
Engineering |
11/13/2008 Approved per Carlos Robles
11/2/09 - 1 year warranty - corrections required per Brandon W. Dirt ramp missing at end of sidewalk.
12/4/09 - 1 year warranty - Approved per Cathy H. |
City Development Engineer |
11/12/08 corrections required per Cathy H. 10% warranty bond. Hillside compliance letter. Electronic dwg of record - missing dimensions to sewer laterals in paper space view. Missing SMH at North boundary in both model and paper space view. Missing main line sewer information through phase 9 to drain Escalera and Red Cliffs Phase 1. per Ken B. Plans show temp turn-a-round which is missing. End of road markers (2) are present and need to be removed.
11/19/08 corrections required per Cathy H. 10% warranty Bond. Electronic DWG of Record - See previous comments. per Ken B. 2010 E is missing temporary turn-around and requires (2) end of road markers to be removed (as per plans).
12/1/08 approved per Ken B.
11/2/09 - 1 year warranty - Corrections required - (Look at public street - Colorado Dr and landscaping.) Per Ken B. Dirt ramp missing at end of sidewalk.
12/4/09 - 1 year warranty - Approved per Cathy H. |
Landscaping |
11/19/2008 Corrections required per Larry Shane.. No street to address no construction, no landscaping along new street as shown on plans.
12/02/2008 Approved per Laura Taylor.. Required street trees and street scape landscaping will be completed for each individual residence at residence construction. Landscape inspection will be required for Final shell inspection.
11/2/09 - 1 year warranty - approved per Ken B. |
| |