Drawing of Record Submitted |
6/19/2009 |
Electronic Drawing |
6/19/2009 |
Final Grading Report |
6/17/2009 |
Date Scheduled |
6/22/2009 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
6/22/09 approved per Dennis W.
4/5/2010 Approved Per Dennis Wright 1 year warranty |
Water |
6/22/2009 Corrections required per Kevin Condie.. 1. Can not find back flow on Irr systemn need to be tested. 2. Concrete around Fire hydrant doesn't meet City Standard 3. Plant & rock in front of hydrant may need to be moved check with Fire Dept. 4. Clean & paint hydrant.
6/25/2009 Approved per Kevin Condie
5/3/10 - 1 year warranty - approved per Kevin Condit - checked locate wire okay 4/28/10. |
Wastewater |
6/22/2009 Corrections required per Kevin Condie.. 1. Can not find back flow on Irr systemn need to be tested. 2. Concrete around Fire hydrant doesn't meet City Standard 3. Plant & rock in front of hydrant may need to be moved check with Fire Dept. 4. Clean & paint hydrant.
6/25/2009 Approved per Kevin Condie
5/3/10 - 1 year warranty - approved per Kevin Condit - checked locate wire okay 4/28/10. |
Engineering |
6/24/2009 Approved per Carlos Robles
4/6/10 - 1 year warranty - approved per Brandon W. |
City Development Engineer |
6/22/09 corrections required per Cathy H. Electronic DWG - Place DWG in city HCN. per Ken B. Missing stop sign at access. Trash enclosure is incomplete. Landscape is incomplete. Curb shoulder is needing replaced at street front (Tabernacle). Construction materials and heavy equipment is on site.
6/23/2009 Approved per Cathy H
4/2/10 - 1 year warranty - approved per Ken B. |
Landscaping |
6/22/09 corrections required per Ken B. Landscape is incomplete at NW corner of property.
6/23/2009 Approved per Cathy H
4/2/10 - 1 year warranty - approved per Ken B. |
| |
General Comments: |
|