Drawing of Record Submitted |
5/26/2009 |
Electronic Drawing |
5/26/2009 |
Final Grading Report |
5/26/2009 |
Date Scheduled |
5/28/2009 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
|
Water |
6/2/2009 Corrections required per Kevin Condie.. Need to check all meter boxes & stetter for water. 2. Turn all valves. 3. Wire - ok 4. Clean & Paint Fire Hydrants
6/15/2009 Approved per Kevin Condie
6/7/2010 Approved per Darrin Judd.. 1 year warranty.. wire good |
Wastewater |
6/2/2009 Corrections required per Kevin Condie.. Need to check all meter boxes & stetter for water. 2. Turn all valves. 3. Wire - ok 4. Clean & Paint Fire Hydrants
6/15/2009 Approved per Kevin Condie
6/7/2010 Approved per Darrin Judd.. 1 year warranty.. wire good |
Engineering |
6/8/2009 Approved per Carlos Robles
5/7/2010 Approved per Brandon Wright 1 year warranty |
City Development Engineer |
5/29/09 corrections required per Cathy H. Provide private development improvement certificate. Electronic DWG of record - provide top and bottom of retaining wall elevations. Provide size, type of pipe, slope etc on storm drain lines. Letter from Rosenberg about adequacy of Atkinville Wash improvements. per Ken B. Missing end of road markers at knuckle end of Heatherglen Drive.
7/6/09 approved per Cathy H.
5/5/10 - 1 year warranty - approved per Cathy H. |
Landscaping |
5/29/09 corrections required per Ken B. Common area park is missing at knuckle on Heatherglen Drive. Other landscape missing at knuckle and on slope at hole 9 (Atkinville wash landscaping).
7/6/09 approved per Cathy H.
5/5/10 - 1 year warranty - approved per Ken B. |
| |
General Comments: |
|