Drawing of Record Submitted |
10/31/2013 |
Electronic Drawing |
10/31/2013 |
Final Grading Report |
10/31/2013 |
Date Scheduled |
11/04/2013 |
BUILDING PERMIT RELEASE APPROVALS |
Power |
|
Water |
|
Wastewater |
|
Engineering |
|
City Development Engineer |
|
Landscaping |
|
FINAL INSPECTION RELEASE APPROVALS |
Power |
11/19/13 approved per Dennis W.
12/03/2014 Approved per Dennis Wright.. 1 yr warranty |
Water |
11/08/2013 Approved per Darrin Judd
11/18/2014 Approved per Kevin Condie 1 yr warranty |
Wastewater |
11/08/2013 Approved per Darrin Judd
11/18/2014 Approved per Kevin Condie 1 yr warranty |
Engineering |
11/4/13 corrections required per Brandon W. Sidewalk not complete. Property corners not installed. Monuments not installed. Cut off drain pipes in DI boxes. Backfill behind sidewalk. Pipe behind sidewalk is not responsibility of City, needs to show on plat.
11/12/2013 Approved per Brandon Wright
12/03/2014 Approved Per Brandon Wright.. 1 year warranty |
City Development Engineer |
11/06/2013 Approved per Jared Stewart.. Streets Dept |
Landscaping |
|
| |
General Comments: |
|