[Silkwood @ Meadow Valley Farms Phase 2]
Number: Grading-41062

Drawing of Record Submitted 7/17/2009..revised 8/3/09
Electronic Drawing 7/17/2009..revised 8/3/09
Final Grading Report 7/23/2009
Date Scheduled 7/29/2009
BUILDING PERMIT RELEASE APPROVALS
Power
Water
Wastewater
Engineering
City Development Engineer
Landscaping
FINAL INSPECTION RELEASE APPROVALS
Power
Water 7/30/2009 Corrections required Per Kevin Condie.. Check wire, check valve open all vaules. check meter setters, clean & paint hydrants 8/4/2009 Approved per Kevin Condie 6/10/2010 Approved per Darrin Judd.. 1 year wararnty.. wire good
Wastewater 7/30/2009 Corrections required Per Kevin Condie.. Check wire, check valve open all vaules. check meter setters, clean & paint hydrants 8/4/2009 Approved per Kevin Condie 6/10/2010 Approved per Darrin Judd.. 1 year wararnty.. wire good
Engineering 8/5/2009 Approved per Brandon Wright 6/7/10 - 1 year warranty approved per Brandon W.
City Development Engineer 7/30/2009 Corrections required per Cathy H..1. Landscape and pave trail in common area between lots 10 & 11 front end of cul0de-sac to roadway. 2. When each home is built, call in for parks inspection to approve. required street trees and street scape along road right- of way. landscape in this are a will be completed with/home construction. 8/4/2009 Corrections required per Cathy H.. 1. Elect Dwg of Record-address why lot 28 still has two sewer laterals. Correct on paper copy also.2. Street lights are still missing. 3. 10% Warranty Bond 8/10/2009 Approved per Ken Bricker 6/4/10 - 1 year warranty approved per Ken B
Landscaping 9/29/2009 Corrections required per Cathy H..1. Electronic Dwg of record-address lots 11 & 28 have two sewer laterals. Lots 11 & 12 are missing sewer lateral dimensions. Also correct on paper copy. 2. Missing both street lights. 3. 10% warranty bond. 8/5/2009 Approved per Ken Bricker 6/4/10 - 1 year warranty approved per Ken B
    
General Comments: